Aragón loses another data center: the electrical connection changes hands

Box2Bit abandons Epilon in Épila and sells 150 MW of connection to Blackstone, which reinforces its Rhodes campus in Calatorao. Energy rules in data centers.

5 min read

In this article

The data center industry in Aragón keeps adding headlines, but not all of them are good news. The latest episode stars Box2Bit, which is withdrawing from the Epilon campus it was going to build in Épila (Zaragoza). With this, three of the company's projects have now fallen through in the region, and the move is not innocuous: the rights to 150 MW of electrical connection capacity have passed into the hands of Blackstone, which will use them to reinforce its Rhodes project in Calatorao.

A trickle of projects that never get built

Let's review the history. The first to fall was the Ebro Campus in Cariñena, valued at 3.4 billion euros, which was left out of the Ministry's investment plan for the next five years. Then came the turn of La Charluca, in Calatayud, which failed to gain access to the transmission grid. And now Epilon, in Épila. Three announcements, three cancellations, and a pattern that is starting to become uncomfortable for anyone who takes the promise of an Aragonese digital ecosystem seriously.

The mayor of Épila, Jesús Bazán, has pointed out that the owners of the nearly 100 hectares reserved did not receive the first payment and that the rights to the land expired last May. Bazán does not rule out that the announcement had speculative motivations: first a project is announced, land rights and connection capacity are obtained, and then those rights are transferred without building anything. It is a hypothesis, not a verdict, but it invites reflection on how this type of operation is managed.

Illustrative detail: Aragón loses another data center: Capital Energy withdraws from Épila and sells its electrical connection to Blackstone

The electrical connection, the asset everyone wants

Beyond the specific case, the news leaves one clear fact: in the data center business, energy is the scarcest and most coveted good. It is not enough to have land or financing; a continuous and powerful electricity supply is needed, and grid connection points have become a transferable asset with value of its own.

Blackstone knows this and has made its move. The 150 MW from Box2Bit are added to the 600 MW that Red Eléctrica had already granted it for Rhodes, the macro-center in Calatorao. The project envisages about 430 MW of computing power and an investment of more than 13 billion euros. The case file documentation, however, records a demand of up to 650 MW expandable to 1,000 MW, far above the 300 MW mentioned at the beginning.

Not everything is a green light for Rhodes

The Superior Court of Justice of Aragón has admitted for processing an appeal by Ecologistas en Acción against the project, according to eldiario.es. The organization questions the partial approval of the Plan of General Interest of Aragón last September 28 and the declaration of public utility, which allows land in rural areas to be expropriated for the benefit of a private developer. Ecologistas en Acción estimates that Rhodes' consumption would be equivalent to 40% of that of the entire region, while the solar plant planned within the site would cover only 0.43% of that demand.

The social tug-of-war is also underway: in Zaragoza there have been demonstrations against data centers with arguments such as that they do not generate employment, do not pay taxes and take the resources. It is a debate worth following closely, because it affects the public perception of the entire industry.

What this means for an SME or an IT team

At first glance, these moves seem like a matter for investment funds and large developers, far removed from the day-to-day of a Sevillian SME. But there are applicable lessons:

  • Infrastructure is neither infinite nor immediate. The announcement of a large campus does not guarantee that it will exist tomorrow. If your digitalization plan depends on computing capacity or cloud services in a specific region, it is advisable to have alternatives and not take for granted what is still up in the air.
  • Energy conditions price and availability. Competition for electrical connection among large projects can put pressure on the market. For an SME, the recommendation is to review supply contracts and assess the energy efficiency of its own equipment, including climate control systems and local servers.
  • Diversify providers and regions. If you depend on a single cloud provider or a single data center, a change of plans like the one in Épila is a reminder that resilience is built with options. Hybrid architectures and backups outside the main provider remain common sense.
  • Read the fine print of announcements. Pharaonic projects that are later canceled or resold teach us to distrust promises without verifiable milestones. This also applies to technology providers: ask for concrete plans, deadlines and responsibilities.

At ForgeNEX we work with SMEs that need technical decisions that are sustainable over time, not spectacular headlines. If you are rethinking your infrastructure or your cloud strategy, let's talk. And if you are interested in how digital sovereignty and AI are reconfiguring the technology map, you can read our analysis on Fsas Technologies and digital sovereignty.

Conclusion: the race for energy redefines the map

Aragón remains an attractive territory for data centers, but the news from Épila shows that the path is not linear. The electrical connection has become the decisive asset, and whoever controls it has an advantage. For SMEs, the practical reading is clear: plan with margin, do not depend on a single provider and treat energy and resilience as part of your IT strategy, not as a technical detail.